Wastewater Treatment Plant


 

Modifications and additions

to the existing Waste Water Treatment Plant, including installation of 2 new clarifiers, centrifuge  dewatering component, sludge handling system, grit removal, a fermenter, additional effluent filtration, 2 new bio-reactors, foul air collection and treatment, ultra-violet disinfection and all electrical, civil and mechanical upgrades.

Concrete structures

include two 18 meter diameter clarifiers, 3.4 million litre capacity Bioreactors, HDPE Lined Screening channels, HDPE lined 10 meter diameter Fermenter addition, a new 2600 sq.ft. sludge building, miscellaneous concrete demolition & upgrades throughout the existing plant.